MISO request J1183

MISO queue ID J1183

Queue request J1183 was listed in the MISO interconnection queue at the end of 2025 as a 1.4 MW solar project in Delta County, MI, according to Berkeley Lab’s queue data file. The filing names Heritage Garden substation as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of October 15, 2019.

Queue IDJ1183
Project nameNot reported
Status (as published)Operational
SubstationHeritage Garden substation
Point of interconnectionHeritage Garden substation
CountyDelta
StateMI
VoltageNot reported
Capacity1.4 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2019-10-15
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Delta, MI: 13 requests in the MISO queue, 6 active totaling 316.3 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityAmerican Transmission Co.
ClusterDPP-2018-APR East (ATC)
Interconnection serviceERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Study Phase: GIA; Post GIA Status: In Service
Queue date2018-03-12
Interconnection agreement date2021-04-02
Operational date2019-10-15

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first