Queue request J1144 was listed in the MISO interconnection queue at the end of 2025 as a 96 MW solar project in Covington County, MS, according to Berkeley Lab’s queue data file. The filing names Moselle - Columbia Line Tap as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 1, 2022.
| Queue ID | J1144 |
|---|---|
| Project name | Not reported |
| Status (as published) | Active |
| Substation | Moselle - Columbia Line Tap |
| Point of interconnection | Moselle - Columbia 161kV Line Tap |
| County | Covington |
| State | MS |
| Voltage | 161 kV |
| Capacity | 96 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Proposed online date | 2022-06-01 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Covington, MS: 3 requests in the MISO queue, 1 active totaling 96 MW.
Tracked changes
Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | COOPERATIVE ENERGY |
|---|---|
| Cluster | DPP-2018-APR South |
| Interconnection service | NRIS |
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | Construction |
| Study phase (as the queue printed it) | Study Phase: GIA; Post GIA Status: Under Construction |
| Queue date | 2018-03-12 |
| Interconnection agreement date | 2020-09-10 |