Substation Scout

MISO request J1125

MISO queue ID J1125

Queue request J1125 was listed in the MISO interconnection queue at the end of 2025 as a 135 MW solar project in Cross County, AR, according to Berkeley Lab’s queue data file. The filing names Wynne South - Wynne East AECC Line Tap as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of March 1, 2023.

Queue IDJ1125
Project nameNot reported
Status (as published)Active
SubstationWynne South - Wynne East AECC Line Tap
Point of interconnectionWynne South - Wynne East AECC 161 kV Line Tap
CountyCross
StateAR
Voltage161 kV
Capacity135 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2023-03-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Cross, AR: 17 requests in the MISO queue, 4 active totaling 605 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityENTERGY ARKANSAS
ClusterDPP-2018-APR South
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Construction
Study phase (as the queue printed it)Study Phase: GIA; Post GIA Status: Under Construction
Queue date2018-03-12
Interconnection agreement date2020-08-12

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.