J3570 Not reported 161 300 Solar Withdrawn
J1857 Not reported n/r 250 Solar Withdrawn
J2577 Not reported n/r 200 Wind Active
J3783 Not reported 161 200 Solar Withdrawn
J3606 Not reported 161 197.7 Hybrid Withdrawn
J3510 Not reported 161 175 Hybrid Withdrawn
J3458 Not reported 161 170 Hybrid Withdrawn
J4036 Not reported n/r 160 Solar Withdrawn
J1125 Not reported 161 135 Solar Active
J1267 Not reported 161 135 Solar Withdrawn
J1816 Not reported 161 135 Solar Active
J1842 Not reported 161 135 Wind Active
J3814 Not reported 161 135 Wind Withdrawn
J677 Not reported n/r 100 Solar Withdrawn
J1841 Not reported 161 52 Wind Withdrawn
J689 Not reported n/r 50 Solar Withdrawn
J1723 Not reported 161 10 Battery Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first