MISO request J1115

MISO queue ID J1115

Queue request J1115 was listed in the MISO interconnection queue at the end of 2025 as a 200 MW wind project in Macon County, IL, according to Berkeley Lab’s queue data file. The filing names Latham - Oreana Line as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of September 1, 2024.

Queue IDJ1115
Project nameNot reported
Status (as published)Active
SubstationLatham - Oreana Line
Point of interconnectionLatham - Oreana 345kV Line
CountyMacon
StateIL
Voltage345 kV
Capacity200 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2024-09-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Macon, IL: 14 requests in the MISO queue, 8 active totaling 1,600.3 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityAMEREN ILLINOIS
ClusterDPP-2018-APR Central
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Construction
Study phase (as the queue printed it)Study Phase: GIA; Post GIA Status: Under Construction
Queue date2018-03-12
Interconnection agreement date2021-10-12

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.