Queue request J1050 was listed in the MISO interconnection queue at the end of 2025 as a 225 MW wind project in Boone County, IA, according to Berkeley Lab’s queue data file. The filing names Doud Tap Substation as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of July 1, 2022.
| Queue ID | J1050 |
|---|---|
| Project name | Not reported |
| Status (as published) | Operational |
| Substation | Doud Tap Substation |
| Point of interconnection | Doud Tap 161 kV Substation |
| County | Boone |
| State | IA |
| Voltage | 161 kV |
| Capacity | 225 MW |
| Resource (as published) | Wind |
| Resource category | Wind (normalized for filtering) |
| Proposed online date | 2022-07-01 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Boone, IA: 6 requests in the MISO queue, 2 active totaling 565 MW.
Tracked changes
Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | ITC MIDWEST |
|---|---|
| Cluster | DPP-2018-APR West |
| Interconnection service | NRIS |
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | IA Executed |
| Study phase (as the queue printed it) | Study Phase: GIA; Post GIA Status: In Service |
| Queue date | 2018-03-12 |
| Interconnection agreement date | 2022-01-17 |
| Operational date | 2022-07-01 |