Queue request J1040 was listed in the MISO interconnection queue at the end of 2025 as a 250 MW wind project in Mcintosh County, ND, according to Berkeley Lab’s queue data file. The filing names Wishek Junction Substation as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of May 14, 2023.

Queue IDJ1040
Project nameNot reported
Status (as published)Active
SubstationWishek Junction Substation
Point of interconnectionWishek Junction 230 kV Substation
CountyMcintosh
StateND
Voltage230 kV
Capacity250 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2023-05-14
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Mcintosh, ND: 11 requests in the MISO queue, 2 active totaling 262 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityMONTANA-DAKOTA UTILITIES CO.
ClusterDPP-2018-APR West
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Construction
Study phase (as the queue printed it)Study Phase: GIA; Post GIA Status: Under Construction
Queue date2018-03-12
Interconnection agreement date2022-02-07

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first