Queue request H093 was listed in the MISO interconnection queue at the end of 2025 as a 5 MW project in Mahoning County, OH, according to Berkeley Lab’s queue data file. The filing names Boardman - Columbia as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of June 1, 2011.

Queue IDH093
Project nameNot reported
Status (as published)Operational
SubstationBoardman - Columbia
Point of interconnectionBoardman - Columbia 69kV
CountyMahoning
StateOH
Voltage69 kV
Capacity5 MW
Resource (as published)Other
Resource categoryOther (normalized for filtering)
Proposed online date2011-06-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Mahoning, OH: 2 requests in the MISO queue, 1 active totaling 5 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterDPP-2008-NOV Individual
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Network Upgrade
Queue date2008-07-25
Interconnection agreement date2010-12-02
Operational date2011-06-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first