Substation Scout

MISO request H009

MISO queue ID H009

Queue request H009 was listed in the MISO interconnection queue at the end of 2025 as a 150 MW wind project in Tama County, IA, according to Berkeley Lab’s queue data file. The filing names ITC Midwest Traer - Marshalltown as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of December 31, 2010.

Queue IDH009
Project nameNot reported
Status (as published)Operational
SubstationITC Midwest Traer - Marshalltown
Point of interconnectionITC Midwest Traer - Marshalltown 161 kV
CountyTama
StateIA
Voltage161 kV
Capacity150 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2010-12-31
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Tama, IA: 12 requests in the MISO queue, 4 active totaling 423.4 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterDPP-2012-AUG WEST
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Network Upgrade
Queue date2008-04-22
Interconnection agreement date2015-04-01
Operational date2010-12-31

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first