Queue request G858 was listed in the MISO interconnection queue at the end of 2025 as a 38 MW wind project in Stearns County, MN, according to Berkeley Lab’s queue data file. The filing names XEL Black Oak Substation as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of December 1, 2009.

Queue IDG858
Project nameNot reported
Status (as published)Operational
SubstationXEL Black Oak Substation
Point of interconnectionXEL Black Oak 69 kV Substation
CountyStearns
StateMN
Voltage69 kV
Capacity38 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2009-12-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Stearns, MN: 10 requests in the MISO queue, 3 active totaling 79 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterDPP-2013-FEB West
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)DPP - SIS
Queue date2013-01-07
Interconnection agreement date2015-05-05
Operational date2009-12-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.