MISO request G741
MISO queue ID G741
Queue request G741 was listed in the MISO interconnection queue at the end of 2025 as a 8 MW hybrid project in Martin County, MN, according to Berkeley Lab’s queue data file. The filing names Near Alliant line as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of March 11, 2011.
| Queue ID | G741 |
|---|---|
| Project name | Not reported |
| Status (as published) | Operational |
| Substation | Near Alliant line |
| Point of interconnection | Near Alliant 69kV line |
| County | Martin |
| State | MN |
| Voltage | 69 kV |
| Capacity | 8 MW |
| Resource (as published) | Geothermal+Other |
| Resource category | Hybrid (normalized for filtering) |
| Proposed online date | 2011-03-11 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Martin, MN: 14 requests in the MISO queue, 7 active totaling 715 MW.
Tracked changes
Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Cluster | DPP-2009-MAR MN |
|---|---|
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | IA Executed |
| Study phase (as the queue printed it) | DPP - SIS |
| Queue date | 2007-02-16 |
| Interconnection agreement date | 2010-03-08 |
| Operational date | 2011-03-11 |
| Components (hybrid) | Geothermal 8 MW + Other |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.