Substation Scout

MISO request G619

MISO queue ID G619

Queue request G619 was listed in the MISO interconnection queue at the end of 2025 as a 50 MW wind project in Otter Tail County, MN, according to Berkeley Lab’s queue data file. The filing names GRE Tamarac Substation as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of December 1, 2008.

Queue IDG619
Project nameNot reported
Status (as published)Operational
SubstationGRE Tamarac Substation
Point of interconnectionGRE Tamarac 41 kV Substation
CountyOtter Tail
StateMN
Voltage41 kV
Capacity50 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2008-12-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Otter Tail, MN: 14 requests in the MISO queue, 7 active totaling 849.6 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterCS5
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)DPP - SIS
Queue date2006-04-14
Interconnection agreement date2009-07-08
Operational date2008-12-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first