Substation Scout

MISO request G543

MISO queue ID G543

Queue request G543 was listed in the MISO interconnection queue at the end of 2025 as a 50 MW coal project in Beaver County, PA, according to Berkeley Lab’s queue data file. The filing names FE Mansfield Three as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of December 1, 2005.

Queue IDG543
Project nameNot reported
Status (as published)Operational
SubstationFE Mansfield Three
Point of interconnectionFE Mansfield Three
CountyBeaver
StatePA
VoltageNot reported
Capacity50 MW
Resource (as published)Coal
Resource categoryCoal (normalized for filtering)
Proposed online date2005-12-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Beaver, PA: 3 requests in the MISO queue, 2 active totaling 100 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Queue date2005-09-02
Interconnection agreement date2006-01-13
Operational date2005-12-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first