Queue request G478 was listed in the MISO interconnection queue at the end of 2025 as a 134 MW gas project in Madison County, IL, according to Berkeley Lab’s queue data file. The filing names Venice Switchyard at breaker position 32H as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of November 1, 2005.

Queue IDG478
Project nameNot reported
Status (as published)Operational
SubstationVenice Switchyard at breaker position 32H
Point of interconnectionVenice Switchyard at breaker position 32H
CountyMadison
StateIL
VoltageNot reported
Capacity134 MW
Resource (as published)Gas
Resource categoryGas (normalized for filtering)
Proposed online date2005-11-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Madison, IL: 3 requests in the MISO queue, 2 active totaling 359 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)SPA - SIS
Queue date2004-10-15
Interconnection agreement date2005-10-11
Operational date2005-11-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first