MISO request G442

MISO queue ID G442

Queue request G442 was listed in the MISO interconnection queue at the end of 2025 as a 50 MW wind project in Cottonwood County, MN, according to Berkeley Lab’s queue data file. The filing names Storden as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of June 1, 2010.

Queue IDG442
Project nameNot reported
Status (as published)Operational
SubstationStorden
Point of interconnectionStorden 69 KV
CountyCottonwood
StateMN
Voltage69 kV
Capacity50 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2010-06-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Cottonwood, MN: 27 requests in the MISO queue, 7 active totaling 1,042 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterG442 G442
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Network Upgrade
Queue date2004-08-18
Interconnection agreement date2005-11-08
Operational date2010-06-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.