Substation Scout

MISO request G355

MISO queue ID G355

Queue request G355 was listed in the MISO interconnection queue at the end of 2025 as a 6 MW project in Muscatine County, IA, according to Berkeley Lab’s queue data file. The filing names West Liberty Muni Sub as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of May 2, 2003.

Queue IDG355
Project nameNot reported
Status (as published)Operational
SubstationWest Liberty Muni Sub
Point of interconnectionWest Liberty Muni Sub 69kV
CountyMuscatine
StateIA
Voltage69 kV
Capacity6 MW
Resource (as published)Diesel
Resource categoryOther (normalized for filtering)
Proposed online date2003-05-02
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Muscatine, IA: 7 requests in the MISO queue, 6 active totaling 585.4 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterG355 G355
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Network Upgrade
Queue date2003-06-27
Interconnection agreement date2004-04-20
Operational date2003-05-02

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.