MISO queue ID G310

Queue request G310 was listed in the MISO interconnection queue at the end of 2025 as a 8 MW wind project in Cerro Gordo County, IA, according to Berkeley Lab’s queue data file. The filing names Cerro Gordo Substation as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of December 1, 2005.

Queue IDG310
Project nameNot reported
Status (as published)Operational
SubstationCerro Gordo Substation
Point of interconnectionCerro Gordo Substation
CountyCerro Gordo
StateIA
VoltageNot reported
Capacity8 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2005-12-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Cerro Gordo, IA: 22 requests in the MISO queue, 8 active totaling 3,339.2 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterG310 G310
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Network Upgrade
Queue date2003-03-18
Interconnection agreement date2004-08-26
Operational date2005-12-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first