Substation Scout

MISO request G278

MISO queue ID G278

Queue request G278 was listed in the MISO interconnection queue at the end of 2025 as a 8 MW wind project in Pipestone County, MN, according to Berkeley Lab’s queue data file. The filing names Pipestone - Dell Rapids as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of May 1, 2007.

Queue IDG278
Project nameNot reported
Status (as published)Operational
SubstationPipestone - Dell Rapids
Point of interconnectionPipestone - Dell Rapids 69kV
CountyPipestone
StateMN
Voltage69 kV
Capacity8 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2007-05-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Pipestone - Dell Rapids substation: 2 requests in the MISO queue, 2 active totaling 12 MW.

Queue IDProjectMWResourceStatus
G185Not reported4WindOperational

Pipestone, MN: 23 requests in the MISO queue, 12 active totaling 293.2 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterG278 G278
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Network Upgrade
Queue date2002-12-19
Interconnection agreement date2005-02-07
Operational date2007-05-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first