MISO queue ID G263

Queue request G263 was listed in the MISO interconnection queue at the end of 2025 as a 105 MW wind project in Martin County, MN, according to Berkeley Lab’s queue data file. The filing names Lakefield Generating Substation as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of November 1, 2007.

Queue IDG263
Project nameNot reported
Status (as published)Operational
SubstationLakefield Generating Substation
Point of interconnectionLakefield Generating Substation
CountyMartin
StateMN
VoltageNot reported
Capacity105 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2007-11-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Martin, MN: 14 requests in the MISO queue, 7 active totaling 715 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterG263 G263
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Network Upgrade
Queue date2002-10-22
Interconnection agreement date2005-05-24
Operational date2007-11-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.