Substation Scout

MISO request G056

MISO queue ID G056

Queue request G056 was listed in the MISO interconnection queue at the end of 2025 as a 80 MW wind project in Hancock County, IA, according to Berkeley Lab’s queue data file. The filing names Sioux Avenue Substation as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of June 1, 2004.

Queue IDG056
Project nameNot reported
Status (as published)Operational
SubstationSioux Avenue Substation
Point of interconnectionSioux Avenue Substation
CountyHancock
StateIA
VoltageNot reported
Capacity80 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2004-06-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Hancock, IA: 16 requests in the MISO queue, 4 active totaling 496 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Queue date2000-09-01
Operational date2004-06-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.