Substation Scout

MISO request G041

MISO queue ID G041

Queue request G041 was listed in the MISO interconnection queue at the end of 2025 as a 2 MW wind project in Pipestone County, MN, according to Berkeley Lab’s queue data file. Its status as of December 31, 2025 was “Operational”, with a proposed online date of June 1, 2004.

Queue IDG041
Project nameNot reported
Status (as published)Operational
SubstationNot reported
Point of interconnectionNot reported
CountyPipestone
StateMN
VoltageNot reported
Capacity2 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2004-06-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Pipestone, MN: 23 requests in the MISO queue, 12 active totaling 293.2 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Queue date2000-05-31
Operational date2004-06-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first