Substation Scout

MISO request G006

MISO queue ID G006

Queue request G006 was listed in the MISO interconnection queue at the end of 2025 as a 2 MW wind project in Clay County, MN, according to Berkeley Lab’s queue data file. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 1, 2004.

Queue IDG006
Project nameNot reported
Status (as published)Active
SubstationNot reported
Point of interconnectionNot reported
CountyClay
StateMN
VoltageNot reported
Capacity2 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2004-06-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Clay, MN: 11 requests in the MISO queue, 4 active totaling 922 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

Project typeGeneration
Study phase (standardized by Berkeley Lab)In Progress (unknown study)
Queue date1999-02-15

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first