Point Coupee (E0051) was listed in the MISO interconnection queue at the end of 2025 as a 377 MW gas project in Pointe Coupee Parish, LA, according to Berkeley Lab’s queue data file. The filing names Big Cajun as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of October 1, 2028.
| Queue ID | E0051 |
|---|---|
| Project name | Point Coupee |
| Status (as published) | Active |
| Substation | Big Cajun |
| Point of interconnection | Big Cajun 500kv |
| County | Pointe Coupee Parish |
| State | LA |
| Voltage | 500 kV |
| Capacity | 377 MW |
| Resource (as published) | Gas |
| Resource category | Gas (normalized for filtering) |
| Proposed online date | 2028-10-01 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Pointe Coupee Parish, LA: 8 requests in the MISO queue, 5 active totaling 842 MW.
Tracked changes
Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | Entergy Louisiana, LLC |
|---|---|
| Developer | Entergy Louisiana, LLC |
| Interconnection service | NRIS |
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | In Progress (unknown study) |
| Study phase (as the queue printed it) | Request Status: Active; Post GIA Status: Not started |
| Queue date | 2025-10-23 |