Mitchell BESS (E0033) was listed in the MISO interconnection queue at the end of 2025 as a 526.7 MW battery project in Lake County, IN, according to Berkeley Lab’s queue data file. The filing names Mitchell Gen. Station as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of August 1, 2028.

Queue IDE0033
Project nameMitchell BESS
Status (as published)Active
SubstationMitchell Gen. Station
Point of interconnectionMitchell Gen. Station
CountyLake
StateIN
VoltageNot reported
Capacity526.7 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2028-08-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Lake, IN: 9 requests in the MISO queue, 7 active totaling 1,426.7 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityNIPSCO
DeveloperNIPSCO
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)In Progress (unknown study)
Study phase (as the queue printed it)Request Status: Active; Post GIA Status: Not started
Queue date2025-08-06

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first