MISO request E0030

MISO queue ID E0030

Queue request E0030 was listed in the MISO interconnection queue at the end of 2025 as a 820 MW gas project in Jefferson County, TX, according to Berkeley Lab’s queue data file. The filing names Legend Substation as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of September 25, 2027.

Queue IDE0030
Project nameNot reported
Status (as published)Active
SubstationLegend Substation
Point of interconnectionLegend 230kV Substation
CountyJefferson
StateTX
Voltage230 kV
Capacity820 MW
Resource (as published)Gas
Resource categoryGas (normalized for filtering)
Proposed online date2027-09-25
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Jefferson, TX: 14 requests in the MISO queue, 2 active totaling 1,108.5 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityEntergy Texas, Inc.
DeveloperEntergy Texas, Inc.
ClusterERAS Study Cycle 2
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)In Progress (unknown study)
Study phase (as the queue printed it)Request Status: Active; Post GIA Status: Not started
Queue date2025-08-06

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.