Substation Scout

Winona, MN interconnection queue

1 active project totaling 4.9 MW in the MISO queue, plus 1 with terminal status (shown grayed).

1active projects
4.9active MW
2total filed
Queue IDProjectkVMWResourceStatus
J112 Not reported 69 4.9 Wind Operational
J126 Not reported 69 4.9 Wind Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.