Webster, IA interconnection queue

4 active projects totaling 820 MW in the MISO queue, plus 4 with terminal status (shown grayed).

4active projects
820active MW
8total filed
Queue IDProjectkVMWResourceStatus
J2436 Not reported 345 300 Wind Active
J3808 Not reported 345 300 Wind Withdrawn
R42 Not reported 345 250 Wind Operational
H020 Not reported n/r 200 Wind Withdrawn
J3926 Not reported 345 170 Wind Active
J2435 Not reported 161 150 Wind Withdrawn
J2323 Not reported 345 145 Wind Withdrawn
J524 Not reported 161 100 Solar Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.