Substation Scout

Scott, MO interconnection queue

3 active projects totaling 556 MW in the MISO queue, plus 4 with terminal status (shown grayed).

3active projects
556active MW
7total filed
Queue IDProjectkVMWResourceStatus
J3690 Not reported 161 300 Battery Withdrawn
J1087 Not reported 161 200 Solar Active
J1299 Not reported 161 200 Solar Active
J3442 Not reported 161 156 Solar Active
J985 Not reported 161 120 Solar Withdrawn
J1161 Not reported 161 100.2 Solar Withdrawn
J2209 Not reported 161 100 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.