Substation Scout

Ralls, MO interconnection queue

2 active projects totaling 375 MW in the MISO queue, plus 3 with terminal status (shown grayed).

2active projects
375active MW
5total filed
Queue IDProjectkVMWResourceStatus
J1489 Not reported 345 500 Other Withdrawn
J1222 Not reported 345 200 Solar Withdrawn
J3720 Not reported 161 200 Solar Withdrawn
J956 Not reported 345 200 Solar Active
J2288 Not reported n/r 175 Solar Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.