Ouachita, AR interconnection queue

5 active projects totaling 1,175.8 MW in the MISO queue, plus 2 with terminal status (shown grayed).

5active projects
1,175.8active MW
7total filed
Queue IDProjectkVMWResourceStatus
J2865 Not reported 500 375 Solar Active
J3040 Not reported 500 365 Solar Active
J4134 Not reported 115 200 Hybrid Active
J2620 Not reported 115 164 Solar Withdrawn
J2818 Not reported 115 130 Hybrid Active
J2634 Not reported 115 105.8 Solar Active
J3164 Not reported 138 100 Battery Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.