Morrison, MN interconnection queue

2 active projects totaling 324 MW in the MISO queue, plus 4 with terminal status (shown grayed).

2active projects
324active MW
6total filed
Queue IDProjectkVMWResourceStatus
J042 Not reported 230 199.8 Wind Withdrawn
J1611 Not reported 115 174 Solar Active
J4157 Not reported 345 150 Wind Active
J1143 Not reported 115 100 Solar Withdrawn
J735 Not reported n/r 100 Solar Withdrawn
G596 Not reported n/r 1 Wind Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.