Substation Scout

Manitowoc, WI interconnection queue

7 active projects totaling 422 MW in the MISO queue, plus 9 with terminal status (shown grayed).

7active projects
422active MW
16total filed
Queue IDProjectkVMWResourceStatus
J383 Not reported n/r 571 Gas Withdrawn
J094 Not reported 138 200 Wind Withdrawn
J2218 Not reported n/r 150 Battery Withdrawn
J886 Not reported 138 150 Solar Operational
J657 Not reported 138 100.8 Wind Withdrawn
G013 Not reported n/r 99 Other Withdrawn
G384 Not reported 138 99 Wind Withdrawn
J505 Not reported 138 99 Solar Operational
G063 Not reported n/r 90 Other Withdrawn
G240 Not reported n/r 55 Gas Operational
G833 Not reported n/r 53 Nuclear Operational
G834 Not reported n/r 53 Nuclear Operational
J1101 Not reported 138 20 Battery Withdrawn
R1002 Replace 11.4 of WPS.LAKEFRN96 Unit with natural gas (with diesel as a backup); Lakefront 9 69 11.4 Hybrid Withdrawn
J022 Not reported n/r 6 Nuclear Operational
J023 Not reported n/r 6 Nuclear Operational

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.