1 active project totaling 150 MW in the MISO queue, plus 4 with terminal status (shown grayed).

1active projects
150active MW
5total filed
Queue IDProjectkVMWResourceStatus
J1578 Not reported 230 200 Solar Withdrawn
J1390 Not reported 230 150 Solar Active
J1624 Not reported 230 100 Solar Withdrawn
J2160 Not reported 230 50 Battery Withdrawn
J491 Not reported 69 20 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.