Substation Scout

Adams, IL interconnection queue

6 active projects totaling 815 MW in the MISO queue, plus 4 with terminal status (shown grayed).

6active projects
815active MW
10total filed
Queue IDProjectkVMWResourceStatus
H079 Not reported 138 200 Wind Withdrawn
J2258 Not reported 138 175 Solar Active
J2203 Not reported n/r 150 Battery Active
J2389 Not reported n/r 150 Hybrid Active
J2627 Not reported n/r 150 Battery Active
J751 Not reported n/r 150 Wind Withdrawn
G598 Not reported 120 144 Wind Withdrawn
G599 Not reported 120 144 Wind Withdrawn
J2972 Not reported 138 140 Solar Active
J2974 Not reported 138 50 Battery Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.