Substation Scout

LG&E and KU request LGE-CS2025-004

LG&E and KU queue ID LGE-CS2025-004

Queue request LGE-CS2025-004 was listed in the LG&E and KU interconnection queue at the end of 2025 as a 200 MW hybrid project in Lincoln County, KY, according to Berkeley Lab’s queue data file. The filing names West Garrard - Pineville line as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of December 31, 2029.

Queue IDLGE-CS2025-004
Project nameNot reported
Status (as published)Active
SubstationWest Garrard - Pineville line
Point of interconnectionWest Garrard - Pineville 345 kV line
CountyLincoln
StateKY
Voltage345 kV
Capacity200 MW
Resource (as published)Solar+Battery
Resource categoryHybrid (normalized for filtering)
Proposed online date2029-12-31
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Lincoln, KY: 4 requests in the LG&E and KU queue, 1 active totaling 200 MW.

Tracked changes

Not tracked. LG&E and KU rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityLouisville Gas & Electric and Kentucky Utilities Energy
ClusterCS 2025
Interconnection serviceNRIS/ERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)In Progress (unknown study)
Queue date2025-12-15
Components (hybrid)Solar 200 MW + Battery

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →