Lincoln, KY interconnection queue
1 active project totaling 200 MW in the LG&E and KU queue, plus 3 with terminal status (shown grayed).
1active projects
200active MW
4total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| LGE-CS2025-004 | Not reported | 345 | 200 | Hybrid | Active |
| LGE-GIS-2022-007 | Not reported | 345 | 150 | Hybrid | Withdrawn |
| LGE-GIS-2022-009 | Not reported | 345 | 100 | Hybrid | Withdrawn |
| LGE-GIS-2008-004 | Not reported | n/r | 6 | Other | Withdrawn |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with LG&E and KU before relying on these figures.