October 15, 2026 · By Phil
Substation voltages and data center power feeds
A primer on distribution vs transmission and what's changed in data center site selection.
Tracking the grid is interesting to me for a number of reasons, not least because it's how I got my start as a site selection professional.
The early part of my career coincided with a large data center build-out in New Jersey to support huge demand from the financial services industry. A quick trip down memory lane (aka Route 287) can tell us a lot about what's happening in the data center industry to support the (way huger) demand we have around the US today.
The short of it is that we used to be able to get by working with utilities to understand their distribution network; but today, we need actual understanding of the transmission network.
tl;dr
Here is a practical summary table that combines PSE&G's recommended ranges with typical industry practice for large loads. Values are approximate and expressed in MW (a kVA or MVA is the nominal value of Volts x Amps, and does not consider the derating necessary to get actual watts out of the equipment).
| Voltage Class | Typical Normal Capacity (per circuit / feeder) | Typical Emergency / Short-term | Notes / Typical Use for Large Loads |
|---|---|---|---|
| 13 kV (distribution) | 4–6 MW (PSE&G upper end ~5 MW) | ~8–12 MW | Multiple parallel feeders common for mid-size loads; limited by feeder thermal rating and substation transformer capacity |
| 26 kV | 10–25+ MW | Higher | PSE&G range starts at ~3 MW and goes much higher; less common for new large customers than 69 kV |
| 69 kV (sub-transmission) | 20–50+ MW (often dual feeds) | Higher | Common for data centers in the 20–100 MW range (see the Sentinel/CyrusOne example below); customer-owned step-down substation usual |
| 138 kV | 50–150+ MW | Higher | Transmission-level service; dual or multi-circuit common; on-site substation required |
| 230 kV | 100–300+ MW | Higher | Standard for many modern hyperscale campuses; dedicated on-site substation (ring or breaker-and-a-half) |
| 345 kV | 200–500+ MW (or more) | Higher | Emerging for the largest AI/hyperscale projects; very large customer or utility substations |
These are rules of thumb, not engineering numbers. What a specific circuit can carry depends on the conductor, the transformers behind it, what else is on it, and a study by the utility. The table is just for getting your bearings.
Back to the Story
- By the early aughts, banks had accumulated massive IT footprints. Most of it did not need to be located right next to the exchanges and people in the metro area.
- Central New Jersey offered a compelling option, because it had cheap real estate and a history of roadway and fiber investments which made it very accessible for people and data.
- But the state is dense and the utility is old and deliberate. Real estate and fiber would be easy enough to find — but energy would require some real due diligence.
- Upcoming distribution upgrades by PSE&G meant that certain areas would soon have superior power access, and young Phil would get some nice deals; what's changed is that nowadays tracking distribution in this way isn't enough, and we need to understand the bigger picture at the transmission level.
On the banks of the old Raritan
The corridor between New York and Philadelphia that the banks went after has been used as an escape route before. In the fall of 1776 George Washington retreated across New Jersey with the British behind him, and he had to get his army over the Raritan at New Brunswick on the way to the Delaware.
The point isn't the history lesson. It's that the Raritan is still in the way. Anything that wants to get from one side of central Jersey to the other, an army or a power line, has to go over the river and through the woods, and river crossings are slow and expensive. So when a utility decides to cross one, that's news worth having early.
Over the river and through the wood
In the 2000s, the news I cared about was PSE&G's new 69kV service. It was going to run east across the Raritan from Bridgewater into Somerset, then over to Piscataway and ultimately Edison, effectively spanning the Bridgewater switch and the Metuchen switch with a few stops in between.
I knew that because I made a habit of regular check-ins with PSE&G and kept the freshest info I could get on where that line was going. It was a sort of Substation Scout before there was one. Back then you had to struggle for that kind of info. Utility maps, property listings and fiber routes never came packaged together, so a broker who showed up with all three for one corridor had something nobody else had.
That habit helped me catch a couple of data center developers, Sentinel and IO, and I was fortunate to help them with site selection along that corridor.
800 Cottontail Lane, Somerset. Sentinel's data center (now CyrusOne) takes 69kV service from two different PSE&G substations and steps it down on site, in a 69kV substation Sentinel built for itself. Two sources means a fault or maintenance outage at one utility station doesn't take out the building. Owning the substation means the developer controls the step-down equipment and how it expands, and also that it gets to be part of a newer and higher-quality 69kV network.
3003 Woodbridge Avenue, Edison. The IO deal was the 830,000sf former New York Times printing plant. It was a monster, but the power story was simpler and strong: the printing plant already had two feeds from the nearby Metuchen switch, a leftover from PSE&G's legacy 26kV distribution system, much of which was upgraded in the early aughts and 2010s. Because Metuchen is one of the state's largest switching stations, additional capacity would be much easier for the utility to accommodate.
One name, two substations
A big station like Metuchen is really two things behind one fence and one name. The top half is a transmission switchyard: 230kV lines from around the region come in, connect through breakers, and leave again. The bottom half is distribution: big transformers step the 230kV down to 26kV or 13kV, and from there a bunch of smaller feeders run out to neighborhoods, office parks and the occasional printing plant.
The two halves are built very differently, and that's the part that matters for a data center.
On the transmission side, the lines connect through a bus arrangement, and a common one is the ring bus: the breakers are wired end to end in a loop, and each line or transformer taps in between two of them. Every connection has two paths around the ring, so you can lose a breaker or work on one without dropping anybody. The catch is that a ring only takes so many connections before it gets hard to protect and operate, commonly somewhere around four to eight positions. When a station outgrows that, utilities often rebuild it as a breaker-and-a-half arrangement, which costs more and scales better.
On the distribution side, it's a lot more flexible. Feeders are smaller and cheaper to add, so a station like Metuchen can have lots of 13kV and 26kV circuits leaving it.
So when the Times building took 26kV from Metuchen, it was taking a feeder off the distribution side. Nobody had to find room for it in the 230kV switchyard.
What's changed
Today's hyperscale projects don't fit on the distribution side anymore. A 300 MW campus would need dozens of 13kV feeders, so it takes service at 138kV, 230kV or 345kV instead, usually with a substation on-site that steps it down, and the meter often sits at that high voltage.
That changes the question a site selector has to answer. When I was doing this, the question was "where are PSE&G's distribution upgrades going, and when?" Today a big project is asking for a position on the transmission system itself: a slot in a switchyard that only has so many, and power that has to be studied and matched with supply across the regional grid, not just the local feeder. That means interconnection queues, large-load studies, and ring buses, none of which I needed to understand in my day.
| Back then | Today | |
|---|---|---|
| Typical initial load | Single-digit MW | Tens to hundreds of MW |
| Service voltage | 13kV or 26kV distribution, sometimes 69kV | 138kV, 230kV, 345kV, even 500kV |
| Who decides | The local utility's distribution planners | The utility's transmission planners, and often the regional grid operator |
| What you track | Distribution upgrades and new feeders | Transmission projects, substation expansions and the interconnection queue |
| What you sign | A load letter | A study agreement and ultimately an Energy Services Agreement |
| How you find out | Regular check-ins with the utility | Public filings, if you can find and read them |
That last row is why I built this site. The information moved from a utility engineer's head to a regional filing system, and the filing system isn't built to be read by people picking sites.