Downie substation interconnection queue

5 active projects totalling 775 MW in the ERCOT queue.

5active projects
775active MW
5total filed
Queue IDProjectkVMWResourceStatus
25INR0195 Photo Solar 2 138 300 Solar SS Completed, FIS Started, No IA
24INR0122 PHOTO BESS 2 138 150 Battery SS Completed, FIS Started, No IA
25INR0194 Photo Solar 1 138 150 Solar SS Completed, FIS Started, No IA
23INR0205 SUNSETTER BESS 138 100 Battery SS Completed, FIS Started, No IA
24INR0121 PHOTO BESS 1 138 75 Battery SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.