ERCOT queue ID 25INR0195 Terminal status
| Queue ID | 25INR0195 |
|---|---|
| Project name | Photo Solar 2 |
| Status (as published) | Cancelled |
| Substation | Downie |
| Point of interconnection | 5885 Downie 138kV |
| County | Uvalde |
| State | TX |
| Voltage | 138 kV |
| Capacity | 300 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2028-05-31 |
| Source dataset | cancelled |
Tracked changes
1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.
| Detected | Change | MW | Status was → now |
|---|---|---|---|
| 2026-10-05 | Terminal status | 300 | SS Completed, FIS Started, No IA → Cancelled |
Additional filed fields
| Fuel Code | Solar |
|---|---|
| Size Category | Large |