Three Ranches Solar

ERCOT queue ID 28INR0271

Queue ID28INR0271
Project nameThree Ranches Solar
Status (as published)SS Completed, FIS Started, No IA
SubstationTAP # Alamitto Creek - # Hayter Ranch
Point of interconnectionTAP 138kV #6680 Alamitto Creek - #60444 Hayter Ranch
CountyBrewster
StateTX
Voltage138 kV
Capacity125.5 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2029-12-01
Source datasetlarge

Additional filed fields

Interconnecting EntityThree Ranches Energy LLC
Cdr ZoneWEST
Fuel CodeSOL
Technology CodePV
Screening Study Complete45789
Water AvailabilityNot Required