Dahlia BESS

ERCOT queue ID 28INR0241 Terminal status

Queue ID28INR0241
Project nameDahlia BESS
Status (as published)Inactive
SubstationTap Los Angeles
Point of interconnectionTap 138 kV 5723 Los Angeles
CountyLa Salle
StateTX
Voltage138 kV
Capacity102.8 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2029-06-30
Source datasetinactive

Tracked changes

1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-09-07 Terminal status 102.8 SS Completed, FIS Started, No IA → Inactive

Full change log →

Additional filed fields

Fuel CodeBattery Storage
Size CategoryLarge