Chimney Creek Solar

ERCOT queue ID 28INR0151

Queue ID28INR0151
Project nameChimney Creek Solar
Status (as published)SS Completed, FIS Started, No IA
SubstationTap West Shackelford – Clear Crossing Ckt 1
Point of interconnectionTap 345 kV 68000 West Shackelford – 60515 Clear Crossing Ckt 1
CountyShackelford
StateTX
Voltage345 kV
Capacity203.9 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2030-05-30
Source datasetlarge

Additional filed fields

Interconnecting EntityChimney Creek Energy, LLC
Cdr ZoneWEST
Fuel CodeSOL
Technology CodePV
Screening Study Complete45789
Water AvailabilityNot Required