Substation Scout

Starlit Pasture Storage

ERCOT queue ID 28INR0095

Queue ID28INR0095
Project nameStarlit Pasture Storage
Status (as published)SS Completed, FIS Started, No IA
SubstationChappell Hill
Point of interconnection7574 Chappell Hill 138 KV
CountyWashington
StateTX
Voltage138 kV
Capacity208.8 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2029-09-30
Source datasetlarge

Additional filed fields

Interconnecting EntityStarlit Pasture Energy Center, LLC
Cdr ZoneSOUTH
Fuel CodeOTH
Technology CodeBA
Screening Study Complete45608

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.