Substation Scout

Starlit Pasture Storage

ERCOT queue ID 28INR0095 Terminal status

Queue ID28INR0095
Project nameStarlit Pasture Storage
Status (as published)Cancelled
SubstationChappell Hill
Point of interconnection7574 Chappell Hill 138 KV
CountyWashington
StateTX
Voltage138 kV
Capacity208.8 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2029-09-30
Source datasetcancelled

Tracked changes

1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-09-07 Terminal status 208.8 SS Completed, FIS Started, No IA → Cancelled

Full change log →

Additional filed fields

Fuel CodeBattery Storage
Size CategoryLarge

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.