Antonio Road BESS

ERCOT queue ID 27INR0090 Terminal status

Queue ID27INR0090
Project nameAntonio Road BESS
Status (as published)Cancelled
SubstationPaige , bus , connecting to the existing substation via adding a breaker
Point of interconnectionPaige 138kV, bus 7308, connecting to the existing substation via adding a breaker
CountyBastrop
StateTX
Voltage138 kV
Capacity155.5 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2027-06-01
Source datasetcancelled

Tracked changes

1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-09-07 Terminal status 155.5 SS Completed, FIS Started, No IA → Cancelled

Full change log →

Additional filed fields

Fuel CodeBattery Storage
Size CategoryLarge

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.