Substation Scout

Post Trail Energy

ERCOT queue ID 26INR0429

Queue ID26INR0429
Project namePost Trail Energy
Status (as published)SS Completed, FIS Started, No IA
SubstationTap Conoco - Black Cat
Point of interconnectionTap 138kV Conoco 8138 - Black Cat 80124
CountyMatagorda
StateTX
Voltage138 kV
Capacity103.5 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2028-10-16
Source datasetlarge

Additional filed fields

Interconnecting EntityPost Trail Energy, LLC
Cdr ZoneCOASTAL
Fuel CodeOTH
Technology CodeBA
Screening Study Complete45634

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.