Jack County III – 345 kV
ERCOT queue ID 26INR0351 Terminal status
| Queue ID | 26INR0351 |
|---|---|
| Project name | Jack County III – 345 kV |
| Status (as published) | Cancelled |
| Substation | Substation Name: JACK COUNTY 2 PLANT |
| Point of interconnection | Substation Name: JACK COUNTY 2 PLANT STATION CODE: JCKCNTY2 BUS NUMBER: 575 |
| County | Jack |
| State | TX |
| Voltage | Not reported |
| Capacity | 660 MW |
| Resource (as published) | GAS/GT |
| Resource category | Gas (normalised for filtering) |
| Target commercial operation | 2027-07-01 |
| Source dataset | cancelled |
Tracked changes
1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.
| Detected | Change | MW | Status was → now |
|---|---|---|---|
| 2026-09-07 | Terminal status | 660 | SS Completed, FIS Started, No IA → Cancelled |
Additional filed fields
| Fuel Code | Gas |
|---|---|
| Size Category | Large |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.