Cairos Solar

ERCOT queue ID 26INR0246

Queue ID26INR0246
Project nameCairos Solar
Status (as published)SS Completed, FIS Started, No IA
SubstationODLAW SWITCH (#)
Point of interconnectionODLAW SWITCH (#7425)
CountyKinney
StateTX
VoltageNot reported
Capacity153.3 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2028-12-31
Source datasetlarge

Additional filed fields

Interconnecting EntityCairos Solar, LLC
Cdr ZoneSOUTH
Fuel CodeSOL
Technology CodePV
Screening Study Complete45290
Water AvailabilityNot Required