Ross Solar

ERCOT queue ID 26INR0155

Queue ID26INR0155
Project nameRoss Solar
Status (as published)SS Completed, FIS Started, IA
Substationtap Angstrom – Static
Point of interconnectiontap 345kV 8249 Angstrom – 8676 Static
CountyRefugio
StateTX
Voltage345 kV
Capacity1,025.6 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2027-07-31
Source datasetlarge

Additional filed fields

Interconnecting EntityS&S Renewables, LLC
Cdr ZoneCOASTAL
Fuel CodeSOL
Technology CodePV
Ia Signed45470
Screening Study Complete45226
Water AvailabilityNot Required