Myers Solar

ERCOT queue ID 26INR0134

Queue ID26INR0134
Project nameMyers Solar
Status (as published)SS Completed, FIS Started, No IA
SubstationBaez
Point of interconnection8629 Baez 69 kV
CountyBee
StateTX
Voltage69 kV
Capacity101.6 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2028-05-22
Source datasetlarge

Additional filed fields

Interconnecting EntityBT Myers Solar, LLC
Cdr ZoneSOUTH
Fuel CodeSOL
Technology CodePV
Screening Study Complete45189
Water AvailabilityNot Required