Substation Scout

Stegall Solar

ERCOT queue ID 25INR0497

Queue ID25INR0497
Project nameStegall Solar
Status (as published)SS Completed, FIS Completed, No IA
SubstationElliott (Bus #53) to Franklin (Bus #57) Transmission Line
Point of interconnectionElliott (Bus #53) to Franklin (Bus #57) 69kV Transmission Line
CountyRobertson
StateTX
Voltage69 kV
Capacity81.6 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2027-05-30
Source datasetlarge

Additional filed fields

Interconnecting EntityBT Martin Solar, LLC
Cdr ZoneNORTH
Fuel CodeSOL
Technology CodePV
Screening Study Complete45236
Fis Approved45875
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.